Hi All

'Actual work' is work actually performed and "Work" is the total work that
was/is scheduled. If the project baseline is saved at the start of the
project, the 'work baseline' equals the scheduled 'work'.

I have been trying out scenarios and noted when the 'actual work' is greater
than the baseline (and the baseline is equal to the 'work') the 'work' is
adjusted to the same total as 'actual work'. Is this correct?

If so, how do I show the extra hours of 'actual work' performed over and
above the baseline? Surely this would impact on my earned value, I am
assuming earned value is calculated from baseline figures, and any variance
of 'actual work' / work is reported against the baseline.

Can someone please provide some guidance?

TIA to all whom respond - Vers
 #2  
02-25-04, 01:22 AM
Gary L. Chefetz [MVP]
Verossa:

Work = Actual work + Remaining work, so at the beginning of a task, work =
work, at the end of a task work = actual work. Baselines don't change once
you set them, unless you change them.
 #3  
02-25-04, 06:01 AM
flyer
Hi, Gary

Excute me
I am still feel confuse with work and actual work on time-sheet
How can I keep the original value of scheduled work on time-shee
when I input different value to actual work

For example
scheduled work is equal to 8 on monday,
It will changed by actual work, if set 2 to actual work
scheduled work=2
Thanks
 #4  
02-25-04, 03:12 PM
Dale Howard [MVP]
Flyer --

When you baseline your project, the Baseline Work values are the original
values you seek. Hope this helps.
 #5  
02-27-04, 09:45 AM
verossa
Hi Gary,

Thanks for responding. I've not had access to the NG so couldn't respond.

Have looked through past posts and figured actual will change work but not
not the baseline. Thanks for confirming this.

Smiles - Vers


"Gary L. Chefetz [MVP]" <garyNOSPAM@chefetzDOTorg> wrote in message
news:a808
[..]
Similar Threads
Scheduled work value changed to match work and actual work values

Hi, Refer the attached document, step 6. "As soon as you entered the first actual value for the task, the scheduled work value changed to match it. Both work and actual...

Actual Work - under or over baseline

Project Server 2003 We are trying develop a report to show us the time entered in a given time frame (usually last week) and whether or not that time is still within...

EPM - time tracking actual hours work vs baseline work hours

With server 2003, can we track each person's actual hours spent vs. what was baselined as their work hours. E.g. I am a project manager, and I have resources from IT and...

Reporting Work Hours (Work, Actual Work, and Remaining Work)

I'm using Project Professional 2003. I'm usually running anywhere from 4 to 8 projects at one time, all pulling from a Resource Pool that I created. I would like to be able...

OLAP values for Baseline Work differ from Project Baseline Work

We have a problem with our OLAP value for total Baseline Work being different than the value in a project. In round numbers, the total Work = 5500 hours, total Baseline Work...


All times are GMT. The time now is 03:03 PM. | Privacy Policy