#1
|
|
|
|
|
Hi,
Refer the attached document, step 6. "As soon as you entered the first actual value for the task, the scheduled work value changed to match it. Both work and actual work values rolled up to the task and summary task levels and were distributed among the specific assignments to the task. You can see this happen in the timephased grid on the right and the table on the left." Here is my question, Could someone explain the above stmt. what it means ? I don't understand what is going on here ? Will appreciate it ? "Scheduled work value changed to match work and actual work values", why ? thanks KS. +-------------------------------------------------------------------+ |Filename: Tracking Progress.pdf | |Download: http://forums.techarena.in/attachmen...chmentid=9185| +-------------------------------------------------------------------+ |
|
|
|
#2
|
|
|
|
|
Hello KS,
When you view work in the Task Usage view, the information in the timescaled portion shows "scheduled work" which is the assignment work as it is currently scheduled. The data is labeled "work" in the view. When you supply actual work, the view updates the "work" value to match the actual work entered. The scheduled work in future days may update if you entered either more or less actual work than was scheduled. The original work value is not lost as it is stored in baseline work, assuming you've saved a baseline before beginning tracking. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project "ks2008" <ks2008.3vj57b> wrote in message news:j57b [..] |
|
|
| Similar Threads | |
| Gantt chart showing actual work past actual work entered The Gantt chart is showing actual work that has not yet been entered. For example, I have enetered actual work to the 18.07.08 yet the Gantt is showing actual work upto... |
|
| Actual Work Doesn't Match I created an analyzer view that is displaying scheduled, availability and actual work by resource and project. I also needed to drill down to the task level so exported the... |
|
| Reporting Work Hours (Work, Actual Work, and Remaining Work) I'm using Project Professional 2003. I'm usually running anywhere from 4 to 8 projects at one time, all pulling from a Resource Pool that I created. I would like to be able... |
|
| Actual work replaces existing actual work for task for resource Hi! I am using Project 2002 Email workgroup to collect actuals from resources. The actual hours reported by the resource for the current week replaces the existing actual... |
|
| Report on Scheduled work vs Actual work by resource Does anyone have any suggestions on the best way to generate a report that shows each resource, the list of tasks they were scheduled to work on, and the list of tasks they... |
|
|