#1
|
|
|
|
|
Hi All,
We are using MS Project Server 2007. I would like to know why there is a difference in Actual Hours reported by Timesheet Cube & MSP_Project_Timesheet cubes? Can this difference be avoided? |
|
|
|
#2
|
|
|
|
|
Vinod:
The Timesheet Cube shows actual work reported through the timesheet. The MSP_Project_Timesheet shows actual work recorded in the Project file. There are numerous reasons why these would not be in sync, including bugs in the Project client that have just recently been resolved in the December 2009 CU. With that said, bugs are the least common reason for discrepancies unless you're using the Project Server setting to restrict updates to actual work from Project Web Access only, which locks down the system rather tightly and not a practical option for many organizations. So for example: Suppose a PM updates a task status directly in the project plan where a resource is assigned. This imputes actual work that will never show in the timesheet cube. As this is a very common practice, in many, if not most cases, you are very likely to see more actual work registered in the project plan than in the timesheets, unless of course, your PMs are also in the habit of deleting completed tasks, which would have the exact opposite impact. |
|
#3
|
|
|
|
|
Gary,
Thank you for the reply. Can I conclude that only Timesheet cube will hold the correct Timesheet data? And is it safe to write a query in Reporting DB which joins Timesheet data and UserViews? |
|
#4
|
|
|
|
|
As long as you're capturing all time through the TS system, then yes, this
is your single source of reliable time information. BTW, this exchange inspired me to write a blog post on this topic. |
|
|
| Similar Threads | |
| Inconsistant hours in Reporting DB and Timesheet cube/Timesheet vi We have been user testing Project Server 2007 incl. timesheet functionality for a while now, where we have created a report (using reporting services against the _Reporting... |
|
| EPM Timesheet versus Timesheet cube (2007) What is the difference between the EPM Timesheet versus the Timesheet cube in Data Analysis? |
|
| EPM2007: Timesheet cube vs. EPM Timesheet cube? Could someone please summarize in a sentence the scope differences between the "Timesheet" cube and the "EPM Timesheet" cube? If there is documentation of this somewhere,... |
|
| Timesheet Cubes I need to build a data analysis view that reports hours spent on administrative tasks (vacation, sick leave, etc.) filtered by RBS. I understand there are 3 cubes containing... |
|
| No Timesheet data coming over to the EPM Timesheet cube We are not able to see our Timesheet data in the EPM Timesheet cube. The data comes over in the Timesheet cube. We have tried just entering time on the timesheet, entering... |
|
|
All times are GMT. The time now is 12:41 PM. | Privacy Policy
|